Monday, July 28, 2008

Update


Soffit and Fascia 7-28- 08


Back Door 7 - 25 - 08


Laying out the kitchen 7 - 23 - 08


Chimney Rock


Front Door - 7 - 14 - 08

Front Door and Rock


Drywall Completed 7-13-08


Drywall Started - 7 - 10 -08


Insulation 7 - 09 -08


Roof 7-07-08


Overflow bath installed - 7-06 -08


Side View of House - 7-4-08


Roofing Started - 7-1-08


Sewer, water, laterals 6-25-08


Framing Complete - 6-19-08


Windows Installed 6-18-08



Roof Progess - 6-10-08


6-08-08


Roof Trusses - 6-06-08

Saturday, June 7, 2008

Trusses and 2nd Floor



It is almost starting to look like the house in the plans

Saturday, May 31, 2008

Master bath

This is the bath in the master bath, overflow heaven!

Final Rock Wall



The rock wall is finished... here are the pictures of the finished product.

5-30-08



We are almost ready to set trusses. This is the view from the upstairs window.

Monday, May 26, 2008

2nd Floor Going Up - 5-26-08


The 2nd floor sub-floor and walls are almost done.

Rock Wall Progress



This is the progress on the rock wall in the back yard. It is a piece of work.

Friday, May 16, 2008

May, 16 - Main Floor Framing

Here are the floor joists installed
Main Floor Walls are almost complete
The view into the valley is breathtaking!

Tuesday, May 13, 2008

Basement Framing May 13, 2008



We started the basement framing on Friday, It will be done today. Main floor sub floors tomorrow.

Tuesday, May 6, 2008

Basement Floors - 5/06/08




We now have a basement and garage floor. It was a great day to pour.

Backfilled




The house is all backfilled and ready to pour the flatwork.

Foundation




Here are the foundation walls being formed and the finish product. These walls were quite a feat. You can also see the damp proofing and the sub plumb going in.